.

 



Volume: 23, Issue: 13 - 07/17/2025

 

A party to a construction contract can waive a right by acting in a manner inconsistent with the enforcement of that right. A party can also waive a right by failing to follow contractual requirements for the enforcement of that right. A municipal project owner in Pennsylvania did both.

 

The owner encouraged a contractor to continue work past the completion deadline and made no mention of assessing the liquidated damages stipulated in the contract. The owner paid the contractor for the continued work with no set-off for liquidated damages. And, the owner failed to comply with the AIA General Conditions that required it to give the contractor written notice of a claim for liquidated damages within 21 days of the initial delay.

 

The second case in this issue called for the Federal Circuit to review the sufficiency of a contractor claim for constructive acceleration of the work schedule. The contractor failed to prove excusable delay on the schedule’s critical path. The government’s grant of a time extension and partial remission of liquidated damages was not evidence of government fault.

 

The third case involved compliance with the statutory requirement that an agreement to arbitrate be in writing. When a written contract form was unsigned by either party, did that comply?


 

A project owner waived its right to liquidated damages by encouraging the contractor to work beyond the schedule’s deadline with no mention of liquidated damages. The owner made progress payments without offsetting liquidated damages and did not assert its claim until after the contractor had completed its work.


 

A contracting officer’s grant of a time extension and partial release of liquidated damages did not establish excusable delay on the schedule’s critical path. The contractor failed to meet its burden of proof regarding constructive acceleration of the work.


 

A state arbitration statute required a written agreement to arbitrate but said nothing about a signed agreement. An Illinois appellate court, persuaded by federal precedent, held that an unsigned written agreement was sufficient.


Volume: 23, Issue: 12 - 06/30/2025

 

Both cases in this issue involve the reasonableness of a period of delay. They arise regarding an owner suspension of the work and an exception to the enforceability of a no-damages-for-delay clause.

 

The federal Suspension of Work clause gives the government the right to suspend work for a “reasonable duration” without any additional compensation to the contractor. Even when a suspension order was clearly justified and expressly contemplated by the contract, the question remained on whether the suspension’s duration became unreasonable.

 

A well-recognized exception to the enforceability of a no-damages-for-delay clause is delay not contemplated by the parties. Even though delay damages were broadly and effectively disclaimed, the question arose on whether a one-year delay in notice-to-proceed was so unreasonable that it was beyond contemplation.


 

To the extent government suspensions of work had been consented to by the contractor or clearly contemplated by the terms of the contract, suspensions could not be considered unreasonable and therefore were not compensable.


 

A one-year delay in the commencement of work was not an “uncontemplated” delay that would vitiate a no-damages-for-delay clause. It is the type of delay, not the duration, that makes a delay uncontemplated by the parties.


Volume: 23, Issue: 11 - 06/16/2025

 

Liquidated damages are intended to compensate a project owner for a contractor’s late completion of the work. What happens, however, when the contractor’s delay is concurrent with owner-caused delay? Traditionally, the owner’s contribution to late completion bars any recovery of liquidated damages. This rule has resulted in part from judicial antipathy toward liquidated damages, an attitude that has dissipated over the decades. Today, apportionment of responsibility is the prevailing approach.

 

A California appeals court was presented with a situation in which a trial court denied a project owner any liquidated damages, suggesting recovery was barred by the owner’s concurrent delay. The appellate court said apportionment of responsibility would have been more appropriate, but the owner had the burden of proving entitlement to liquidated damages. And, the owner had presented no scheduling evidence that would have made apportionment possible.

 

The second case in this issue involves responsibility for interior tenant improvements in a new commercial building. Those improvements were excluded from the contractor’s scope of work. However, the contract’s Changes clause was triggered when the owner directed the contractor to perform the improvements. This obligated the contractor to follow the procedures stipulated in the clause.

 

The third case addresses a Montana statute establishing an alternative dispute resolution procedure encouraging pre-litigation settlement of residential construction disputes. The state Supreme Court ruled the statute did not create a new legal cause of action for “construction defects.”


 

The factual record did not establish or allow an apportionment of responsibility for critical path delay. Consequently, the project owner was denied recovery of liquidated damages. The contractor had been responsible for some delay, but that delay had been concurrent with owner-caused delay.


 

While interior tenant improvements were not included in an original contract, the owner’s insistence the contractor perform the improvements within the guaranteed maximum price was a directed change. The contractor had been obligated to comply with the procedural provisions of the Changes clause.


<< PREVIOUS PAGE   Page: 1 of 293   NEXT PAGE >>

 

 

 


WPL
PUBLISHING CO, INC.
WPL Publishing - 5750 Bou Avenue #1712 - Rockville, MD 20852

Phone: (301)983-0443  -  Fax: (301)983-4367

All Content and Design Copyright © 2025 WPL Publishing
About Us

Contact Us

Privacy Policy

My Account